Sam's RV-14A Build
Home
(6381 Total Hrs)
Avionics
(164.5 Hrs)
Empennage
(16 Hrs)
Fuselage
(8.5 Hrs)
Fwf
(112.5 Hrs)
Inventory
(4 Hrs)
Other
(71 Hrs)
Section 10
(57 Hrs)
Section 11
(6 Hrs)
Section 12
(4.5 Hrs)
Section 14
(5 Hrs)
Section 17
(9.5 Hrs)
Section 19
(4 Hrs)
Section 20
(28 Hrs)
Section 22
(5.5 Hrs)
Section 23
(15 Hrs)
Section 24
(5.5 Hrs)
Section 25
(5.5 Hrs)
Section 29
(5.5 Hrs)
Section 30
(19.5 Hrs)
Section 31
(14 Hrs)
Section 32
(22 Hrs)
Section 33
(9 Hrs)
Section 34
(6.5 Hrs)
Section 36
(20.5 Hrs)
Section 37
(15 Hrs)
Section 38
(96 Hrs)
Section 39
(3.5 Hrs)
Section 40
(11 Hrs)
Section 41
(5.5 Hrs)
Section 43
(25 Hrs)
Section 44
(17.5 Hrs)
Section 45
(21.5 Hrs)
Section 46
(43.5 Hrs)
Section 47
(2 Hrs)
Section 50
(6 Hrs)
Section 53
(5.5 Hrs)
Section 55
(4.5 Hrs)
Section 56
(2.5 Hrs)
Section 6
(8 Hrs)
Section 60
(5 Hrs)
Section 63
(3.5 Hrs)
Section 7
(19 Hrs)
Section 8
(31 Hrs)
Section 9
(48 Hrs)
Wings
(71 Hrs)
Rigged aileron pushrods, stated wing tips
9 Jan 2023
4 hours
Section 23
Share
Assemble and install oil cooler
6 Jan 2023
4.5 hours
FWF
Share
Fabricated and installed aileron bellcranks
6 Jan 2023
5.5 hours
Section 23
Share
Assembled all heat exchangers. Installed all Zacatecas tubes for heat system. Installed heat Shields. Installed EGT and CHT sensors. Rerouted and secured breather tube.
5 Jan 2023
5.5 hours
FWF
Share
Attached flaps and ailerons, started aileron push rods
5 Jan 2023
5.5 hours
Section 22
Share
Completed exhaust install. Started heat exchanger installation.
4 Jan 2023
5 hours
FWF
Share
Used RTV to seal gaps between engine and baffles. Cut heater Scat tubes. Placed cabin heat “T”. Assembled exhaust tubes and prepared for installation.
3 Jan 2023
5 hours
FWF
Share
Installed inlet baffles and prop governor foam
30 Dec 2022
5 hours
Section 45
Share
Clecoed all rubber to baffles. Install magneto blast tubes.
29 Dec 2022
2 hours
FWF
Share
Installed and sealed heat shield. Riveted baffles. Started flap installation
29 Dec 2022
5 hours
Section 45
Share
� 2020
Design
pdevty