Sam's RV-14A Build
Home
(1063.5 Total Hrs)
Avionics
(164.5 Hrs)
Empennage
(16 Hrs)
Fuselage
(8.5 Hrs)
Fwf
(112.5 Hrs)
Inventory
(4 Hrs)
Other
(71 Hrs)
Section 10
(57 Hrs)
Section 11
(6 Hrs)
Section 12
(4.5 Hrs)
Section 14
(5 Hrs)
Section 17
(9.5 Hrs)
Section 19
(4 Hrs)
Section 20
(28 Hrs)
Section 22
(5.5 Hrs)
Section 23
(15 Hrs)
Section 24
(5.5 Hrs)
Section 25
(5.5 Hrs)
Section 29
(5.5 Hrs)
Section 30
(19.5 Hrs)
Section 31
(14 Hrs)
Section 32
(22 Hrs)
Section 33
(9 Hrs)
Section 34
(6.5 Hrs)
Section 36
(20.5 Hrs)
Section 37
(15 Hrs)
Section 38
(96 Hrs)
Section 39
(3.5 Hrs)
Section 40
(11 Hrs)
Section 41
(5.5 Hrs)
Section 43
(25 Hrs)
Section 44
(17.5 Hrs)
Section 45
(21.5 Hrs)
Section 46
(43.5 Hrs)
Section 47
(2 Hrs)
Section 50
(6 Hrs)
Section 53
(5.5 Hrs)
Section 55
(4.5 Hrs)
Section 56
(2.5 Hrs)
Section 6
(8 Hrs)
Section 60
(5 Hrs)
Section 63
(3.5 Hrs)
Section 7
(19 Hrs)
Section 8
(31 Hrs)
Section 9
(48 Hrs)
Wings
(71 Hrs)
Finished riveting tailcone
21 Jun 2021
6 hours
Section 10
Share
Finished static lines. Finished tailcone wiring. Drilled VS to aft tailcone
16 Jun 2021
2 hours
Section 10
Share
Completed tailcone wiring. Installed Static Lines. Installed rudder cables. Riveted aft deck. Dimpled remaining tailcone skins
14 Jun 2021
8.5 hours
Section 10
Share
Completed riveting lower tailcone
10 Jun 2021
6.5 hours
Section 10
Share
Riveted left side tail cone skin
9 Jun 2021
2.5 hours
Section 10
Share
Rivet aft bottom skin to bulkheads. Installed tail spring bracket
8 Jun 2021
3 hours
Section 10
Share
Clecoed side skins. Ran wire harness. Cutout tail spring hole in aft bottom skin. Fit and match drill tail spring bracket.
7 Jun 2021
6.5 hours
Section 10
Share
Dimpled and riveted bottom tailcone skin. Dimpled stiffeners. Countersunk longerons. Dimpled aft side skins
3 Jun 2021
6.5 hours
Section 10
Share
Worked on the aft fuselage bulkheads
2 Jun 2021
5 hours
Section 10
Share
Prepped and primed all tailcone parts
1 Jun 2021
5 hours
Section 10
Share