Sam's RV-14A Build
Home
(5317.5 Total Hrs)
Avionics
(164.5 Hrs)
Empennage
(16 Hrs)
Fuselage
(8.5 Hrs)
Fwf
(112.5 Hrs)
Inventory
(4 Hrs)
Other
(71 Hrs)
Section 10
(57 Hrs)
Section 11
(6 Hrs)
Section 12
(4.5 Hrs)
Section 14
(5 Hrs)
Section 17
(9.5 Hrs)
Section 19
(4 Hrs)
Section 20
(28 Hrs)
Section 22
(5.5 Hrs)
Section 23
(15 Hrs)
Section 24
(5.5 Hrs)
Section 25
(5.5 Hrs)
Section 29
(5.5 Hrs)
Section 30
(19.5 Hrs)
Section 31
(14 Hrs)
Section 32
(22 Hrs)
Section 33
(9 Hrs)
Section 34
(6.5 Hrs)
Section 36
(20.5 Hrs)
Section 37
(15 Hrs)
Section 38
(96 Hrs)
Section 39
(3.5 Hrs)
Section 40
(11 Hrs)
Section 41
(5.5 Hrs)
Section 43
(25 Hrs)
Section 44
(17.5 Hrs)
Section 45
(21.5 Hrs)
Section 46
(43.5 Hrs)
Section 47
(2 Hrs)
Section 50
(6 Hrs)
Section 53
(5.5 Hrs)
Section 55
(4.5 Hrs)
Section 56
(2.5 Hrs)
Section 6
(8 Hrs)
Section 60
(5 Hrs)
Section 63
(3.5 Hrs)
Section 7
(19 Hrs)
Section 8
(31 Hrs)
Section 9
(48 Hrs)
Wings
(71 Hrs)
Connected tack wire. Completed assembly of all backshells. Connected and tested right P-Mag. Ran all P-mag manifold pressure lines. Installed Pilot and co-Pilot screens. Install pitot, AOA, and static lines.
19 Jan 2023
8.5 hours
FWF
Share
Nav lights, aileron servi
19 Jan 2023
4.5 hours
Section 55
Share
Finished right wing tip lens. Installed wing tip ribs. Started nav light installation
18 Jan 2023
5.5 hours
Section 25
Share
Completed CHT and EGT wiring and tested for function. Wired starter to switch. Wired left P-Mag and tested.
17 Jan 2023
6 hours
Avionics
Share
Drilled, countersunk and attached nut plates on left wing tip. Started wing tip lens
17 Jan 2023
5.5 hours
Section 23
Share
Continued wiring EGTs and CHTs.
16 Jan 2023
2.5 hours
FWF
Share
Wired oil temp sensor. Ran wires for
11 Jan 2023
2.5 hours
FWF
Share
Installed sniffle valve hoses. Injected and configured prop governor and alternate air cables. Started wiring oil temp probe.
10 Jan 2023
5 hours
FWF
Share
Trimmed wing tip lens. Trimmed, drilled, countersunk and installed nut plates on right wing tip
10 Jan 2023
5.5 hours
Section 24
Share
Installed hoses to oil cooler. Installed oil cooler scat tube. Connected manifold pressure.
9 Jan 2023
5.5 hours
FWF
Share