Sam's RV-14A Build
Home
(3190.5 Total Hrs)
Avionics
(164.5 Hrs)
Empennage
(16 Hrs)
Fuselage
(8.5 Hrs)
Fwf
(112.5 Hrs)
Inventory
(4 Hrs)
Other
(71 Hrs)
Section 10
(57 Hrs)
Section 11
(6 Hrs)
Section 12
(4.5 Hrs)
Section 14
(5 Hrs)
Section 17
(9.5 Hrs)
Section 19
(4 Hrs)
Section 20
(28 Hrs)
Section 22
(5.5 Hrs)
Section 23
(15 Hrs)
Section 24
(5.5 Hrs)
Section 25
(5.5 Hrs)
Section 29
(5.5 Hrs)
Section 30
(19.5 Hrs)
Section 31
(14 Hrs)
Section 32
(22 Hrs)
Section 33
(9 Hrs)
Section 34
(6.5 Hrs)
Section 36
(20.5 Hrs)
Section 37
(15 Hrs)
Section 38
(96 Hrs)
Section 39
(3.5 Hrs)
Section 40
(11 Hrs)
Section 41
(5.5 Hrs)
Section 43
(25 Hrs)
Section 44
(17.5 Hrs)
Section 45
(21.5 Hrs)
Section 46
(43.5 Hrs)
Section 47
(2 Hrs)
Section 50
(6 Hrs)
Section 53
(5.5 Hrs)
Section 55
(4.5 Hrs)
Section 56
(2.5 Hrs)
Section 6
(8 Hrs)
Section 60
(5 Hrs)
Section 63
(3.5 Hrs)
Section 7
(19 Hrs)
Section 8
(31 Hrs)
Section 9
(48 Hrs)
Wings
(71 Hrs)
Finished aileron pushrods and tested operation. Started landing light installation. Worked on empennage and wing root fairings.
10 Feb 2023
7 hours
Wings
Share
Attached rudder faring. Assembled pushrods for ailerons. Install left flap pushrod.
9 Feb 2023
5 hours
Wings
Share
Fabricated fuel lines. Started center aileron pushrod installation
9 Feb 2023
2 hours
Other
Share
Connect electrical and pitot/AOA to wings. Fixed swapped wires. Tested operation. Sand and paint vertical and horizontal stab tips. Torque wing bolts.
7 Feb 2023
4.5 hours
Wings
Share
Painted interior parts
7 Feb 2023
2.5 hours
Other
Share
Fiberglass rudder fairing and vertical stabilizer cap. Install wings. Pressure test left tank.
6 Feb 2023
5 hours
Wings
Share
Worked on rudder fairing. Worked on vertical stabilizer fiberglass.
3 Feb 2023
4 hours
Empennage
Share
Started horizontal stabilizer tip installation. Mounted rudder and tested operation. Finalized ELT installation.
2 Feb 2023
6 hours
Empennage
Share
Finish installing nut plates on empennage. Install vertical stabilizer. Install elevators. Wired strobe/position light.
31 Jan 2023
6 hours
Empennage
Share
Rudder and Elevator fairings. Shaved HS stab for elevator clearance
31 Jan 2023
4.5 hours
Section 12
Share
� 2020